Installation of steel structure workshop
1.Foundation construction (pre-embedded anchor bolts), detail need to according to the foundation construction drawing.
2.Column installation One worker commands truck crane how to move, 3 ~ 4 workers cooperate with crane to install the steel column, put column to anchor bolt location.
3.Beam installation After completing the installation of adjacent two steel column, then main beam begin to install.
4.Installing roof & wall purlin The roof and wall purlin will be installed after finishing column and beam. Bolting the purlin on the main structure.
5.Fixing wall and roof sheet To fix the wall sheet on wall purlin by self-tapping screw; then fix the roof sheet.
6.Fixing the cover To install the cover on the corner, eave, window and door opening.
7.Install windows and doors.